Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 290 Topic 30 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 290 Topic 30 Discussion

PMP Exam Topic 30 Question 290 Discussion:
Question #: 290
Topic #: 30

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?


A.

Assign this member to facilitate the next meeting to ensure project team collaboration.


B.

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.


C.

Review and update the project ground rules to make meeting attendance mandatory.


D.

Understand the reason for the team member's absence and encourage them to attend future meetings.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.