Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 262 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 262 Topic 27 Discussion

PMP Exam Topic 27 Question 262 Discussion:
Question #: 262
Topic #: 27

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp


A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet


B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine


C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers


D.

Meet with the key stakeholders to identify the proper product concept for the development team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.