Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 262 Topic 27 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 262 Topic 27 Discussion

PMP Exam Topic 27 Question 262 Discussion:
Question #: 262
Topic #: 27

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?


A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue


B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact


C.

Monitor Risks, to install system performance monitoring tools and update the risk register


D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.