Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 263 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 263 Topic 27 Discussion

PMP Exam Topic 27 Question 263 Discussion:
Question #: 263
Topic #: 27

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?


A.

Request a replacement for those team members who are unhappy with this way ofworking.


B.

Schedule a session with the product owner to explain that no support items can betaken into the sprints going forward.


C.

Ask human resources (HR) to send the team members to a change managementworkshop.


D.

Schedule a session with the team to discuss the issues and work with them to define aplan to manage the sprints going forward.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.