PMI Project Management Professional (2025 Version) PMP Question # 263 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 263 Topic 27 Discussion

PMP Exam Topic 27 Question 263 Discussion:
Question #: 263
Topic #: 27

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?


A.

Start sending status updates to this stakeholder based on the request.


B.

Ask the stakeholder's manager if the stakeholder can be added to the list.


C.

Review the stakeholder engagement and communications management plans.


D.

Escalate the stakeholder’s request to the project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.