PMI Project Management Professional (2025 Version) PMP Question # 264 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 264 Topic 27 Discussion

PMP Exam Topic 27 Question 264 Discussion:
Question #: 264
Topic #: 27

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?


A.

Ask the project sponsor to replace the contractor since they do not have agile experience


B.

Issue a formal notice to the contractor to obtain an agile certification


C.

Consult the project team to understand the extent of the training needs for the contractor


D.

Instruct the contractor to receive agile training since the project has already started


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.