Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 264 Topic 27 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 264 Topic 27 Discussion

PMP Exam Topic 27 Question 264 Discussion:
Question #: 264
Topic #: 27

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?


A.

Inform the team not to accept any changes, as it involves significant rework.


B.

Request management to update the project requirements accordingly.


C.

Request an update of only new requirements, as other changes involve rework.


D.

Inform management that the agreed-upon scope cannot be changed.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.