PMI Project Management Professional (2025 Version) PMP Question # 279 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 279 Topic 28 Discussion

PMP Exam Topic 28 Question 279 Discussion:
Question #: 279
Topic #: 28

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?


A.

Network diagram


B.

Decomposition


C.

Work breakdown structure (WBS)


D.

Resource leveling


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.