Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 267 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 267 Topic 27 Discussion

PMP Exam Topic 27 Question 267 Discussion:
Question #: 267
Topic #: 27

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?


A.

Engage the project team In implementing and Improving key aspects of the standup meetings.


B.

Ask the product owner to remove team members who do not comply with standup meeting rules.


C.

Send a daily retrospective report to all team members instead of holding standup meetings.


D.

Include a daily brainstorming session In the standup meetings to resolve pending Issues.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.