Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 267 Topic 27 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 267 Topic 27 Discussion

PMP Exam Topic 27 Question 267 Discussion:
Question #: 267
Topic #: 27

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?


A.

Keep activities as planned regardless of the resource change.


B.

Update the burndown chart to reflect this resource's absence.


C.

Have a meeting with the resource to understand the issue.


D.

Request an additional resource to finish the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.