Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 8 out of 13 pages
Viewing questions 351-400 out of questions
Questions # 351:

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

Options:

A.

Emphasize to the teams the importance of meeting the agreed deadlines


B.

Provide appropriate training to compensate for the mismatch.


C.

Update the project schedule to reflect the delay


D.

Accept the risk of the project missing deadlines due to the mismatch.


Expert Solution
Questions # 352:

After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

Options:

A.

Share the customer feedback with the project team


B.

Follow the meeting agenda and make a list of the next deliverables


C.

Document this feedback in the meeting minutes.


D.

Start planning how to improve the dates of next deliverables


Expert Solution
Questions # 353:

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

Options:

A.

Organize regular meetings with all of the deployment teams to share issues and solutions


B.

Propose that some of the teams delay deployments in their countries


C.

Ask the project sponsor to appoint new managers for the deployment teams


D.

Ask each deployment team to provide a very detailed schedule and action plan


Expert Solution
Questions # 354:

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

Options:

A.

Set up a training session for all project team members


B.

Reach out to the functional managers for support


C.

Speak individually with each project team member about making the needed updates


D.

Send an email asking all project team members to complete updates at the end of the day


Expert Solution
Questions # 355:

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.


B.

Speak with individual team members to determine what they would like to do to improve the situation in the team


C.

Have the team inform senior management of the situation and ask for recommendations.


D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct


Expert Solution
Questions # 356:

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.

Add the competitor's functionalities to the product backlog to improve the product


B.

Ask the sponsor to add more people to the team


C.

Help the team to find a new approach to launch the product as soon as possible


D.

Ask the team to increase the velocity to launch the product as soon as possible


Expert Solution
Questions # 357:

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

Options:

A.

Award certificates of appreciation to encourage the team


B.

Inform the team about the delivery pressure from the project sponsor


C.

Send a formal notice to team members instructing them to maintain performance


D.

Hire a few temporary team members to help with the additional work.


Expert Solution
Questions # 358:

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance


D.

Explain to the stakeholder that the stakeholder engagement plan requires theirattendance at all reviews


Expert Solution
Questions # 359:

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

Options:

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them


B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.


C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report


D.

Research which templates of reports were used the most for this framework and incorporate them into the project


Expert Solution
Questions # 360:

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

Options:

A.

Clarify project benefits with the sponsor.


B.

Identify the goal of each work product


C.

Perform integration testing of each release


D.

Include the entire project team in testing


Expert Solution
Questions # 361:

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk

What should the project manager do first to facilitate the approval of project requirements'?

Options:

A.

Review the project charter


B.

Perform a stakeholder analysis


C.

Identify the source of the disagreement


D.

Hold a team-building event


Expert Solution
Questions # 362:

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Ask for advice on how to be a better mentor to these team members.


B.

Set up a team building event to bring synergy back to the project team.


C.

Adjust the project manager's management style to better fit senior team members.


D.

Meet daily with each senior team member to monitor project status


Expert Solution
Questions # 363:

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Options:

A.

Remove the changes to match the original requirements.


B.

Add team members to the project to avoid more schedule delays.


C.

Evaluate the impacts of the changes that were made to the project


D.

Update project documentation with the new scope


Expert Solution
Questions # 364:

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

Options:

A.

Perform a risk assessment and define a risk response action plan.


B.

Proceed with the project using management reserves to cover any delays or losses.


C.

Propose a pause in this phase to save labor costs and asset depreciation.


D.

Establish new partnerships with other suppliers in anticipation of any delays.


Expert Solution
Questions # 365:

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

Options:

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.


B.

Speak with the project sponsor about changing the team composition


C.

Figure out who is behind the issues and apply progressive disciplinary techniques.


D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside


Expert Solution
Questions # 366:

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?

Options:

A.

Schedule a meeting with the project team to reinforce the ground rules.


B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action


C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.


D.

Ask the functional manager to replace team members not following the ground rules


Expert Solution
Questions # 367:

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

Options:

A.

Autocratic decision making


B.

Expert judgment


C.

Context diagram


D.

Change control tools


Expert Solution
Questions # 368:

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

Options:

A.

Ask the marketing director to participate in daily meetings


B.

Mentor the marketing director on hybrid approaches


C.

Ask the marketing team members to coach the director


D.

Tram the marketing team and keep the director informed


Expert Solution
Questions # 369:

A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two)

Options:

A.

Revisit the team's discussion on team behaviors and norms


B.

Report to the project manager about the new team member’s behavior


C.

Coach the new team member to improve engagement with the team.


D.

Force the new team member to participate in activities that are considered easy


E.

Facilitate an open discussion on all ideas and perspectives


Expert Solution
Questions # 370:

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Options:

A.

Ensured the risk tolerance of the company was property updated


B.

Implemented the communications management plan properly


C.

Implemented the stakeholder engagement plan correctly.


D.

Provided a proper risk response


Expert Solution
Questions # 371:

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)

Options:

A.

Conduct a stakeholder analysis.


B.

Reinforce team communication.


C.

Update the project management plan with the new timeline


D.

Adopt an incremental approach


E.

Leverage work between team members


Expert Solution
Questions # 372:

A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?

Options:

A.

An agile approach as this would provide working functionality earlier


B.

A predictive approach as this would please the senior stakeholders


C.

A hybrid project as this will mitigate stakeholders' concerns.


D.

A predictive approach as this will show benefits for all stakeholders


Expert Solution
Questions # 373:

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?

Options:

A.

Implement crashing to compress the schedule and improve the schedule performance index (SRI).


B.

Implement fast-tracking to compress the schedule and improve the SPI


C.

Perform conflict management using the project's resource management plan.


D.

Review the risk management plan to evaluate the probability and impact of these delays


Expert Solution
Questions # 374:

A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects

What should the project manager do?

Options:

A.

Schedule a steering committee meeting and obtain their approval on the request


B.

Support the decisions of the team and transfer the decision making responsibility to them.


C.

Inform the team that although this is a hybrid environment, the project managermust still be responsible for making decisions


D.

Consult the product owner about letting the resources make decisions


Expert Solution
Questions # 375:

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

Options:

A.

Encourage all team members to use a virtual workspace


B.

Ask the team to send emails with detailed task progress


C.

Talk to the team member about their engagement and take appropriate action.


D.

Reassign the work to a resource who participates in the daily calls


E.

Report the team member’s poor performance to the functional manager


Expert Solution
Questions # 376:

Drag the to the correct scenario on the right

Question # 376


Expert Solution
Questions # 377:

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement

What should the project manager do next?

Options:

A.

Escalate the issue to the project sponsor and add it to the risk register


B.

Refuse to work on the project because management is not following standard project management practices


C.

Meet with management to explain the potential problems with running a project without a project scope statement


D.

Start the project with inputs from the project charter to save time


Expert Solution
Questions # 378:

Drag the organizational characteristics on the left to the correct scenario on the right

Question # 378


Expert Solution
Questions # 379:

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

Options:

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session


B.

Contact the project sponsor and request new team members who are familiar with adaptive projects


C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project


D.

Freeze the design stage and look for an external resource to run iterative design at extra cost


Expert Solution
Questions # 380:

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

Options:

A.

Sprint charter


B.

Burndown chart


C.

Company mission and vision


D.

Product backlog


E.

Sprint goal


Expert Solution
Questions # 381:

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

Question # 381


Expert Solution
Questions # 382:

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future


B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing


C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch


D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision


Expert Solution
Questions # 383:

A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects

What should the project manager do to ensure the project scope is completely defined?

Options:

A.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk.


B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements


C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations


D.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products


Expert Solution
Questions # 384:

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.


B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly


C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties


D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer


Expert Solution
Questions # 385:

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

Options:

A.

Coach those team members lacking hybrid knowledge to learn on the job.


B.

Change the team to include hybrid experts


C.

Assess the required training per team member.


D.

Deliver hybrid training to all team members


Expert Solution
Questions # 386:

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily


B.

Decrease the sprint cycle to the average repriontization request by calculating it in days


C.

Set up a meeting with the project team and ask for their opinion on what to do


D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle


Expert Solution
Questions # 387:

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Options:

A.

Check the approved list of requirements to see if there are any missing items.


B.

Work with the stakeholder to improve the requirements' acceptance criteria


C.

Review the requirements traceability matrix with the concerned stakeholder


D.

Discuss with the stakeholder which additional requirements should be added


Expert Solution
Questions # 388:

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond’

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor forassistance


D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews


Expert Solution
Questions # 389:

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.

The project is an information technology project and has minimal impact to the organization


B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).


C.

The project scope is well defined and the requirements are prioritized


D.

The project team has a colocated space and is capable of working together


Expert Solution
Questions # 390:

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace


B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly


C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan


D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap


Expert Solution
Questions # 391:

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

Options:

A.

Update the issue log and escalate to the project sponsor


B.

Identify the lack of information as a risk and update the risk register


C.

Schedule more frequent meetings with the technical manager.


D.

Review and update the stakeholder engagement plan


Expert Solution
Questions # 392:

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

Options:

A.

Create a stakeholder engagement plan


B.

Design a communications management plan


C.

Update the team charter accordingly.


D.

Set up a meeting to discuss accommodations the team will have to make


Expert Solution
Questions # 393:

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project


B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register


C.

Refer to the stakeholder register from the previous project as it was similar to the current project


D.

Document in the risk register that the current project may have differentstakeholders than the previous project


Expert Solution
Questions # 394:

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

Options:

A.

Review lessons learned from previous projects that used the same team


B.

Review the organizational culture, structure, and governance


C.

Coordinate a meeting to understand the situation and resolve any conflicts.


D.

Coordinate a meeting with regional managers to ask for support


Expert Solution
Questions # 395:

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)

Options:

A.

Establish daily standups to review project progress and track the completion of deliverables


B.

Allow the team members to catch up at their own pace


C.

Alert the business stakeholders immediately of the schedule delay.


D.

Discuss the risk of project delay and work priorities with the respective functional managers


E.

Work with the team to identify options to accelerate project delivery.


Expert Solution
Questions # 396:

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?

Options:

A.

Reviewed the communications management plan before inviting an external client representative to the meeting


B.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting


C.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register


D.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting


Expert Solution
Questions # 397:

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?

Options:

A.

Project audit


B.

Lessons learned


C.

Organizational process assets


D.

Procurement audit


Expert Solution
Questions # 398:

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Question # 398


Expert Solution
Questions # 399:

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Question # 399


Expert Solution
Questions # 400:

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

Options:

A.

Involved the business stakeholders in the sprint review


B.

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits


C.

Implemented a closing survey for key stakeholders


D.

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success


Expert Solution
Viewing page 8 out of 13 pages
Viewing questions 351-400 out of questions