A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?
A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?
A team identifies a critical set of tasks that have not been included in the Kanban board, and there is not enough budget for the work hours needed to complete the activities. What solution should the agile project manager implement?
A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?
A project lead conducted coordination meetings to estimate the budget and confirm the timeframe for a new project. Due to internal resource challenges, outsourcing some activities could be implemented during execution. What should the project lead ensure before submitting the project for a stage gate review to receive the needed investment?
An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?
A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?
A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?
After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?
During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?
A project to develop a new service is initiated by a telecommunications operator. The project management plan was developed, approved, and shared with respective stakeholders. What should the project manager do next?
A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?
A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?
A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?
The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?
A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?
Throughout the project, the project manager consistently checks the work performance data and finds that two stakeholders are not engaged in the project as expected. In addition, another stakeholder always complains that they are often involved in irrelevant meetings. What should the project manager do first?
A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?
A project manager is leading a team delivering new software to a finance team. The new software will streamline the finance team’s monthly closing activities and reporting. What should the project manager use to promote knowledge transfer for the new solution?
A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?
A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?
There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?
During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?
A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?
During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?
An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?
A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?
The project team has reviewed the requirements and identified some concerns. The project sponsor has asked the team how they will handle each concern. What should the project manager do next?
Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?
A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?
A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?
During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?
A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?
A project manager is working on a multinational project with stakeholders from different regions. What should the project manager do first to ensure there is effective stakeholder collaboration?
A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
Which two actions should a project manager consider while launching a new virtual team? (Choose two)
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch
On what should the project manager focus?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.
What should the project manager do first?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?
The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.
What should the project manager do?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting
What should the project manager have done to avoid this situation?
A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company
What should the project manager have the Scrum team do to recover from these issues?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project
What should the project manager do?
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished
What should the project manager have done differently?