PMI Project Management Professional (2025 Version) PMP Question # 389 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 389 Topic 39 Discussion

PMP Exam Topic 39 Question 389 Discussion:
Question #: 389
Topic #: 39

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?


A.

Reschedule the project taking this new information into account.


B.

Refer to the project's resource management plan.


C.

Ask the project sponsor for external resources.


D.

Create a change request to be validated by the project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.