PMI Project Management Professional (2025 Version) PMP Question # 390 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 390 Topic 40 Discussion

PMP Exam Topic 40 Question 390 Discussion:
Question #: 390
Topic #: 40

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?


A.

Use interpersonal skills to expedite the issue.


B.

Send a gentle reminder to the technical service team.


C.

Update the issue log with the status and priority.


D.

Issue a formal warning to the technical service team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.