Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 390 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 390 Topic 40 Discussion

PMP Exam Topic 40 Question 390 Discussion:
Question #: 390
Topic #: 40

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?


A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace


B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly


C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan


D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.