Question #: 388
Topic #: 39

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?


A.

Inform the team not to accept any changes, as it involves significant rework.


B.

Request management to update the project requirements accordingly.


C.

Request an update of only new requirements, as other changes involve rework.


D.

Inform management that the agreed-upon scope cannot be changed.