Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 388 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 388 Topic 39 Discussion

PMP Exam Topic 39 Question 388 Discussion:
Question #: 388
Topic #: 39

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond’


A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor forassistance


D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.