Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 387 Topic 39 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 387 Topic 39 Discussion

PMP Exam Topic 39 Question 387 Discussion:
Question #: 387
Topic #: 39

Which two actions should a project manager consider while launching a new virtual team? (Choose two)


A.

Recruit the best resources within the organization to be part of the virtual team


B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls


C.

Identify the types and quantities of resources required for each work package or activity


D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress


E.

Verify if team members are on more than one team and cannot devote enough time to this team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.