Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 387 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 387 Topic 39 Discussion

PMP Exam Topic 39 Question 387 Discussion:
Question #: 387
Topic #: 39

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?


A.

Check the approved list of requirements to see if there are any missing items.


B.

Work with the stakeholder to improve the requirements' acceptance criteria


C.

Review the requirements traceability matrix with the concerned stakeholder


D.

Discuss with the stakeholder which additional requirements should be added


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.