PMI Project Management Professional (2025 Version) PMP Question # 386 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 386 Topic 39 Discussion

PMP Exam Topic 39 Question 386 Discussion:
Question #: 386
Topic #: 39

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?


A.

The organizational process assets (OPAs) have been updated.


B.

The contractual deliverables of the project have been accepted.


C.

It The handover and deliverable acceptance have been completed.


D.

The lessons learned sessions have been conducted.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.