Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 386 Topic 39 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 386 Topic 39 Discussion

PMP Exam Topic 39 Question 386 Discussion:
Question #: 386
Topic #: 39

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)


A.

Contact the team member's functional manager and invite them to the next retrospective


B.

Meet with the entire team to review the ground rules about safe environments


C.

Meet with the product owner to talk about the situation.


D.

Contact the team member to explain what information can be shared outside the team


E.

Meet with the sponsor to review the situation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.