Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 385 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 385 Topic 39 Discussion

PMP Exam Topic 39 Question 385 Discussion:
Question #: 385
Topic #: 39

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?


A.

Coach those team members lacking hybrid knowledge to learn on the job.


B.

Change the team to include hybrid experts


C.

Assess the required training per team member.


D.

Deliver hybrid training to all team members


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.