PMI Project Management Professional (2025 Version) PMP Question # 385 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 385 Topic 39 Discussion

PMP Exam Topic 39 Question 385 Discussion:
Question #: 385
Topic #: 39

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?


A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed


B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early


C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated


D.

In the initiation process, as it happens concurrently with the project contract and project charter creation


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.