Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 384 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 384 Topic 39 Discussion

PMP Exam Topic 39 Question 384 Discussion:
Question #: 384
Topic #: 39

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?


A.

Ask the customer to issue a change request with the information to analyze and provide a solution.


B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly


C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties


D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.