PMI Project Management Professional (2025 Version) PMP Question # 384 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 384 Topic 39 Discussion

PMP Exam Topic 39 Question 384 Discussion:
Question #: 384
Topic #: 39

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?


A.

Ensure the content of the project report is clearly understood and request any necessary feedback.


B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.


C.

Send a detailed report to each steering committee member ahead of the meeting.


D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.