Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 397 Topic 40 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 397 Topic 40 Discussion

PMP Exam Topic 40 Question 397 Discussion:
Question #: 397
Topic #: 40

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?


A.

Develop a work plan for the project team member with the help of the resource manager


B.

Advise the functional manager and the project team member to review the resource management plan


C.

Tell the functional manager and the project team member to review the projectcharter


D.

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.