Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 397 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 397 Topic 40 Discussion

PMP Exam Topic 40 Question 397 Discussion:
Question #: 397
Topic #: 40

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?


A.

Project audit


B.

Lessons learned


C.

Organizational process assets


D.

Procurement audit


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.