PMI Project Management Professional (2025 Version) PMP Question # 399 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 399 Topic 40 Discussion

PMP Exam Topic 40 Question 399 Discussion:
Question #: 399
Topic #: 40

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?


A.

Create better plans to test the functionality in more detail.


B.

Review the definition of done (DoD) with the product owner.


C.

Include previous sprint defects and close them in the actual sprint.


D.

Get approval from the product owner on the user stories.