PMI Project Management Professional (2025 Version) PMP Question # 395 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 395 Topic 40 Discussion

PMP Exam Topic 40 Question 395 Discussion:
Question #: 395
Topic #: 40

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?


A.

Report the impediment to the functional manager.


B.

Identify the impediment and associated risks at the daily standup.


C.

Escalate the impediment and associated risks to the business sponsor.


D.

Identify the impediment during the retrospective


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.