Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 395 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 395 Topic 40 Discussion

PMP Exam Topic 40 Question 395 Discussion:
Question #: 395
Topic #: 40

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)


A.

Establish daily standups to review project progress and track the completion of deliverables


B.

Allow the team members to catch up at their own pace


C.

Alert the business stakeholders immediately of the schedule delay.


D.

Discuss the risk of project delay and work priorities with the respective functional managers


E.

Work with the team to identify options to accelerate project delivery.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.