Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 393 Topic 40 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 393 Topic 40 Discussion

PMP Exam Topic 40 Question 393 Discussion:
Question #: 393
Topic #: 40

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?


A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project


B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register


C.

Refer to the stakeholder register from the previous project as it was similar to the current project


D.

Document in the risk register that the current project may have differentstakeholders than the previous project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.