Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 372 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 372 Topic 38 Discussion

PMP Exam Topic 38 Question 372 Discussion:
Question #: 372
Topic #: 38

A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?


A.

An agile approach as this would provide working functionality earlier


B.

A predictive approach as this would please the senior stakeholders


C.

A hybrid project as this will mitigate stakeholders' concerns.


D.

A predictive approach as this will show benefits for all stakeholders


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.