PMI Project Management Professional (2025 Version) PMP Question # 372 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 372 Topic 38 Discussion

PMP Exam Topic 38 Question 372 Discussion:
Question #: 372
Topic #: 38

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?


A.

Review the adaptive tools' impact and obtain agreement from the functional manager.


B.

Follow the functional manager's recommendation to implement only predictive tools in the project.


C.

Make the decision on which project approach to use that would best fit the project.


D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.