PMI Project Management Professional (PMBOK 7th Version) PMP Question # 374 Topic 38 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 374 Topic 38 Discussion

PMP Exam Topic 38 Question 374 Discussion:
Question #: 374
Topic #: 38

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?


A.

Assign a business analyst to build detailed requirements so the project manager can estimate the project duration


B.

Explain that the team will build a production prototype model to help the customer visualize how the features should work


C.

Add extra time and resources to the estimating phase to accommodate the lack of requirements


D.

Raise a risk that scoping and estimating will be delayed if the customer cannot approve requirements