PMI Project Management Professional (2025 Version) PMP Question # 373 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 373 Topic 38 Discussion

PMP Exam Topic 38 Question 373 Discussion:
Question #: 373
Topic #: 38

During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?


A.

Discuss this issue with the project sponsor to request additional funding to implement mitigation


B.

Hire a construction management consultant to develop a comprehensive site execution plan


C.

Prequalify contractors with proven track records to eliminate productivity concerns


D.

Add construction productivity to the risk register and develop a mitigation strategy for site execution


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.