Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 373 Topic 38 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 373 Topic 38 Discussion

PMP Exam Topic 38 Question 373 Discussion:
Question #: 373
Topic #: 38

During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?


A.

Obtain the acceptance criteria from the product owner.


B.

Encourage the team to do pair programming to reduce testing.


C.

Ensure the definition of done (DoD) is understood by all team members.


D.

Involve a quality assurance (QA) expert to support the testing estimation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.