PMI Project Management Professional (2025 Version) PMP Question # 378 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 378 Topic 38 Discussion

PMP Exam Topic 38 Question 378 Discussion:
Question #: 378
Topic #: 38

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?


A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed


B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.


C.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.


D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.