Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 377 Topic 38 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 377 Topic 38 Discussion

PMP Exam Topic 38 Question 377 Discussion:
Question #: 377
Topic #: 38

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?


A.

Perform a make-or-buy analysis


B.

Review the statement of work (SOW)


C.

Leverage the enterprise environmental factors (EEFs)


D.

Refer to the organizational process assets (OPAs)


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.