Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement

What should the project manager do next?


A.

Escalate the issue to the project sponsor and add it to the risk register


B.

Refuse to work on the project because management is not following standard project management practices


C.

Meet with management to explain the potential problems with running a project without a project scope statement


D.

Start the project with inputs from the project charter to save time