Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 375 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 375 Topic 38 Discussion

PMP Exam Topic 38 Question 375 Discussion:
Question #: 375
Topic #: 38

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)


A.

Encourage all team members to use a virtual workspace


B.

Ask the team to send emails with detailed task progress


C.

Talk to the team member about their engagement and take appropriate action.


D.

Reassign the work to a resource who participates in the daily calls


E.

Report the team member’s poor performance to the functional manager


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.