PMI Project Management Professional (2025 Version) PMP Question # 375 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 375 Topic 38 Discussion

PMP Exam Topic 38 Question 375 Discussion:
Question #: 375
Topic #: 38

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?


A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.


B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.


C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.


D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.