PMI Project Management Professional (2025 Version) PMP Question # 381 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 381 Topic 39 Discussion

PMP Exam Topic 39 Question 381 Discussion:
Question #: 381
Topic #: 39

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?


A.

Inform the functional manager that self-organization includes task allocation.


B.

Confirm with the team members that the functional manager is responsible for the delivery.


C.

Ask the product owner to clarify the roles and responsibilities of the project team.


D.

Inform the functional manager that task allocation is the responsibility of the product owner.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.