Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 381 Topic 39 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 381 Topic 39 Discussion

PMP Exam Topic 39 Question 381 Discussion:
Question #: 381
Topic #: 39

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?


A.

Meet with project stakeholders to define a mitigation plan


B.

Register the issue and escalate it to the project sponsor


C.

Estimate the cost of changing the project location


D.

Execute the contingency plan defined in the risk management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.