Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 380 Topic 39 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 380 Topic 39 Discussion

PMP Exam Topic 39 Question 380 Discussion:
Question #: 380
Topic #: 39

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?


A.

Create a list of the tasks and send it to the project sponsor for review and approval.


B.

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.


C.

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.


D.

Prepare a resource management plan that details all the resources needed to complete the tasks.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.