PMI Project Management Professional (2025 Version) PMP Question # 382 Topic 39 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 382 Topic 39 Discussion

PMP Exam Topic 39 Question 382 Discussion:
Question #: 382
Topic #: 39

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?


A.

Escalate the obstacle to a servant leader for resolution.


B.

Ignore the obstacle and present the partial solution to the customer


C.

Focus on generating business value despite the obstacle


D.

Make changes to reprioritize the backlog because of the obstacle.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.