During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?


A.

Use a network diagram to show that the delayed tasks are not on the critical path.


B.

Use a network diagram to show the task duration and dependencies among tasks.


C.

Use a Gantt chart to compare the actual schedule with the planned project schedule.


D.

Use a resource histogram to show that the resources are adequate to complete all tasks on time.