PMI Project Management Professional (2025 Version) PMP Question # 368 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 368 Topic 37 Discussion

PMP Exam Topic 37 Question 368 Discussion:
Question #: 368
Topic #: 37

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?


A.

Risk register information


B.

Higher-level activities completed


C.

Milestones status report


D.

Resource breakdown structure (RBS)


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.