PMP Exam Topic 38 Question 370 Discussion:
Question #: 370
Topic #: 38

A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?


A.

Increase the sprint duration to accommodate the additional work


B.

Conduct a root cause analysis before addressing the issue


C.

Escalate the issue to the stakeholder's functional manager


D.

Cancel the one-on-one sessions and obtain the information via email