PMI Project Management Professional (2025 Version) PMP Question # 370 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 370 Topic 38 Discussion

PMP Exam Topic 38 Question 370 Discussion:
Question #: 370
Topic #: 38

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?


A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.


B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other external

stakeholders.


C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.


D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to the

government.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.