Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 370 Topic 38 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 370 Topic 38 Discussion

PMP Exam Topic 38 Question 370 Discussion:
Question #: 370
Topic #: 38

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?


A.

Ensured the risk tolerance of the company was property updated


B.

Implemented the communications management plan properly


C.

Implemented the stakeholder engagement plan correctly.


D.

Provided a proper risk response


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.