Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 366 Topic 37 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 366 Topic 37 Discussion

PMP Exam Topic 37 Question 366 Discussion:
Question #: 366
Topic #: 37

A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?


A.

Host a team meeting and ask the team to fix any quality issues immediately since the stakeholders’ needs are the main focus.


B.

Request a subject matter expert (SME) from the project sponsor to identify and address the quality issues with the team.


C.

Facilitate a discussion and come to an agreement about what quality means for both the team and the stakeholders.


D.

Schedule a quality retrospective and discuss the challenges that resulted in poor initial quality with the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.