Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 366 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 366 Topic 37 Discussion

PMP Exam Topic 37 Question 366 Discussion:
Question #: 366
Topic #: 37

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?


A.

Schedule a meeting with the project team to reinforce the ground rules.


B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action


C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.


D.

Ask the functional manager to replace team members not following the ground rules


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.