PMI Project Management Professional (2025 Version) PMP Question # 366 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 366 Topic 37 Discussion

PMP Exam Topic 37 Question 366 Discussion:
Question #: 366
Topic #: 37

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)


A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.


B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.


C.

Update the communications management plan and encourage the teams to review it promptly and proactively.


D.

Create a status reporting template and share it with all team members before the day ends.


E.

Schedule daily meetings with each team to understand their progress and concerns in detail.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.