PMI Project Management Professional (2025 Version) PMP Question # 367 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 367 Topic 37 Discussion

PMP Exam Topic 37 Question 367 Discussion:
Question #: 367
Topic #: 37

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?


A.

Use a business case to model a sales pitch and gain consensus from the sponsors.


B.

Request help from the project sponsor to get support from the sales agents.


C.

Escalate the issue to senior management to gain team buy-in


D.

Explain the change benefits to the sales agents' manager to get their support.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.