Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 367 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 367 Topic 37 Discussion

PMP Exam Topic 37 Question 367 Discussion:
Question #: 367
Topic #: 37

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?


A.

Autocratic decision making


B.

Expert judgment


C.

Context diagram


D.

Change control tools


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.