PMP Exam Topic 40 Question 394 Discussion:
Question #: 394
Topic #: 40

A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway

through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?


A.

Communicated with the two team members that the purpose of the training is to provide material that might be useful to them in the future


B.

Sent an immediate request to the human resources (HR) department to replace the current team members with higher skilled candidates


C.

Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand


D.

Planned a training to follow the specific course to bring the two team members to the required experience level