Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 3 out of 13 pages
Viewing questions 101-150 out of questions
Questions # 101:

A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.

What should the project manager do moving forward?

Options:

A.

Provide clear expectations around task requirements.


B.

Review the task list with the team on a regular basis,


C.

Provide templates for the product owner to use in the future.


D.

Review the task with the sponsor to see if they are satisfied.


Expert Solution
Questions # 102:

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has

been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?

Options:

A.

Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.


B.

Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.


C.

Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.


D.

Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.


Expert Solution
Questions # 103:

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

Options:

A.

Appoint a dedicated product manager for the duration of the release


B.

Have the customer approve the product increment features.


C.

Ensure every user story has acceptance criteria.


D.

Track business outcomes for planned user stories.


Expert Solution
Questions # 104:

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

Question # 104


Expert Solution
Questions # 105:

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase


B.

Inform the quality team that they need to ensure that the product is in compliance


C.

Ensure that compliance is explicitly mentioned in the relevant requirements


D.

Meet with the team and remind them of the compliance requirements


Expert Solution
Questions # 106:

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.

Work with the product owner to evaluate and prioritize the requirements


B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list


C.

Determine the expected benefits of each requirement to maximize the overall business value


D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders


Expert Solution
Questions # 107:

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information


B.

Scope statement


C.

Issue log


D.

Risk register


Expert Solution
Questions # 108:

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.

Instruct the team members involved to resolve the issue among themselves


B.

Discuss the issue with the steering committee to determine the proper course of action.


C.

Coordinate a video conference with the offending team member to resolve the issue


D.

Reassign the offending team member to a different project


Expert Solution
Questions # 109:

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.

Facilitate a team-building meeting to help this issue


B.

Allow the team members to remain in their former individual roles


C.

Directly guide the team members on how to perform their tasks


D.

Wait until some iterations are completed to intervene


Expert Solution
Questions # 110:

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates


B.

Check the ground rules of the meeting to review the initial agreement with the team members


C.

Identify one team representative to speak up during the daily meeting and share the team updates


D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak


Expert Solution
Questions # 111:

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

Options:

A.

Ask the team to solve the issue internally and review the underperforming resource's situation


B.

Meet with the team member privately to discuss the problem and work together to find a solution


C.

Contact the functional manager and request to replace the team member with a better resource


D.

Discuss various options to improve the team member's performance with their functional managers


Expert Solution
Questions # 112:

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.

Review the project scope to align the project teams


B.

Review the resource management plan to align the project teams


C.

Review the project integration plan to align the project teams


D.

Review the work breakdown structure (WBS) to align the project teams


Expert Solution
Questions # 113:

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

Options:

A.

Inform executive management that the customer is made aware of the status duringthe sprint demo.


B.

Prepare a weekly status report and share it with executive management every week.


C.

Inform executive management about agile principles and processes that are followedin the project.


D.

Ask the team to prepare and share the status report with executive management everyweek.


Expert Solution
Questions # 114:

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.

Maintain a central repository of artifacts with a version control system.


B.

Maintain separate document control via regions to avoid discrepancies.


C.

Develop a document management software for version control.


D.

Facilitate training on version control and project artifacts,


Expert Solution
Questions # 115:

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage


B.

Add more float to the overall project schedule


C.

Request additional contingency from the sponsor.


D.

Organize a root cause analysis (RCA) workshop.


Expert Solution
Questions # 116:

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

Options:

A.

Assess and evaluate the team member's skills to ensure alignment to the particular requirement and solution


B.

Reassign the requirement to another team member who may have ideas on how to meet the requirement


C.

Assist by connecting the product owner with the team member to discuss what problem is to be solved


D.

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity


Expert Solution
Questions # 117:

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

Options:

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint


B.

Ask the team to address this at the next sprint planning instead of at the retrospective


C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance


D.

Work with the product owner to remove the story from the sprint because the points cannot be splits


Expert Solution
Questions # 118:

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project


B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful


C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor


D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project


Expert Solution
Questions # 119:

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.


B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.


C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.


D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.


Expert Solution
Questions # 120:

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

Options:

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.


B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.


C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,


D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner


Expert Solution
Questions # 121:

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story


B.

Average the story points provided by each team member for a story


C.

Continue multiple rounds of planning poker and arrive at the size of the story


D.

Collaborate with different teams and arrive at the size of the story


Expert Solution
Questions # 122:

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

Options:

A.

Rolling wave planning and an adaptive approach


B.

Relative estimation to determine the task or deliverable sizes


C.

Iterations and reviews to continuously keep adapting the plan


D.

Bottom-up estimating based on a work breakdown structure (WBS)


E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects


Expert Solution
Questions # 123:

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.

Confront the people causing the stress directly with the aim of finding amicable solutions


B.

Seek support from the project management office (PMO) on addressing issues affecting the project


C.

Discuss the possible actions with the project sponsor


D.

Avoid the people causing stress and request a transfer as soon as possible


E.

Talk to the human resources (HR) manager about these concerns


Expert Solution
Questions # 124:

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.

Shared


B.

Accepted


C.

Enhanced


D.

Exploited


Expert Solution
Questions # 125:

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Options:

A.

Inform the stakeholder that they must level their knowledge with other stakeholders.


B.

Update the risk register with the potential impact and apprise the steering committee.


C.

Inform the project management office (PMO) that the team will use a predictive approach for this project.


D.

Allocate time to mentor the stakeholder in the selected project approach.


Expert Solution
Questions # 126:

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.

Resource breakdown structure


B.

Work breakdown structure (WBS)


C.

Team charter


D.

Project charter


Expert Solution
Questions # 127:

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned


B.

Meet with the technical lead to review the sprint plan


C.

Meet with the product owner to confirm the minimum viable product (MVP) option


D.

Meet with the project team and reprioritize the backlog


Expert Solution
Questions # 128:

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

Options:

A.

Fast tracking


B.

Resource leveling


C.

Critical chain method


D.

Schedule crashing


Expert Solution
Questions # 129:

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Question # 129


Expert Solution
Questions # 130:

During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?

Options:

A.

Capacity analysis


B.

Benefits analysis


C.

Risk analysis


D.

Gap analysis


Expert Solution
Questions # 131:

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Options:

A.

Meet with each team member separately and apply an appropriate approach with each one.


B.

Approach the project sponsor and request help in discussing the project deliverables with team members.


C.

Explain to the team that the project manager is ultimately responsible for the delivery.


D.

Assign multiple managers to the various teams and delegate all of the tasks to them.


Expert Solution
Questions # 132:

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.

Meet with all project stakeholders to identify how to implement the technology.


B.

Identify the disagreement in the risk register and develop a contingency plan.


C.

Update the project charter to align with the desires of the project sponsor.


D.

Negotiate with the project sponsor to develop a mutually beneficial solution.


Expert Solution
Questions # 133:

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

Options:

A.

Update the risk register in order to add the issue.


B.

Review the issue log regarding the concern


C.

Revise the benefits management plan


D.

Assess the repository to check for inconsistencies.


Expert Solution
Questions # 134:

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

Options:

A.

Propose using a compliance review board that will be responsible for approving allproduct features prior to their release to the public.


B.

Liaison with the compliance group, making them responsible for understanding therequirements and keeping them prioritized in the backlog.


C.

Meet with the compliance team and make sure that their requirements are covered in thedefinition of done (DoD) for each story.


D.

Ensure that the peer review process also covers compliance requirements, creating asecond layer of security for the project.


Expert Solution
Questions # 135:

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities


B.

Conduct serial activities on tasks


C.

Increase the number of standup meetings


D.

Perform tasks in parallel


Expert Solution
Questions # 136:

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.


B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.


C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,


D.

Check with procurement to see if there is another previously used contractor who can develop the task.


Expert Solution
Questions # 137:

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

Options:

A.

Confirmed that the communication was understood and solicited feedback from the team


B.

Sent the roles and responsibilities matrix along with the project management plan


C.

Discussed the roles with the managers to help explain them to their team members


D.

Briefed each team member on their roles before sending the project management plan


Expert Solution
Questions # 138:

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.

Explore the minimum requirements of the product and their feasibility.


B.

Explain the resource constraints of the project to management.


C.

Outsource the management of the product to an external team.


D.

Conduct a detailed risk analysis to highlight the risks in the project.


Expert Solution
Questions # 139:

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute toprojects.


B.

Assign employees to agile projects so they can quickly adjust to the new approach.


C.

Train all employees in agile approaches.


D.

Shift the way the company views, reviews, and assesses employees.


Expert Solution
Questions # 140:

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

Options:

A.

Remind the team that their primary responsibility is software development.


B.

Add a user story to the product backlog to test the software product.


C.

Discuss the Option in the next daily standup meeting to finalize the decision.


D.

Recommend the option to the product owner for consideration.


Expert Solution
Questions # 141:

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.

Start scheduling the training for key workers now to ensure compliance.


B.

Maintain the current key workers since the project has already started.


C.

Update the project charter to ensure the new legislation is addressed,


D.

Start a recruitment drive for new workers with the licenses required.


Expert Solution
Questions # 142:

A customer asks the project manager about opportunities to create business value.

What should the project manager do first in order to provide the customer with an appropriate

response?

Options:

A.

Examine the business value throughout the project.


B.

Ask the team to organize a spike to identify more value.


C.

Meet with the product owner to review the backlog.


D.

Meet with the sponsor to review the business case.


Expert Solution
Questions # 143:

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.


B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.


C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.


D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.


Expert Solution
Questions # 144:

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.

Quality


B.

Estimates


C.

Objectives


D.

Requirements


Expert Solution
Questions # 145:

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.

Ask the team member to send their concerns in writing.


B.

Empathize with the team member and discuss next steps.


C.

Review the organization's human resources (HR) policy.


D.

Schedule a meeting with the team member for the next work day.


Expert Solution
Questions # 146:

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.


B.

Set up a meeting with the team member to review the team charter.


C.

Ask another team member to meet with this team member for a discussion.


D.

Send a reminder to the team member about the rule being violated.


Expert Solution
Questions # 147:

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.

Update the scope management plan to track the new government requirements.


B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.


C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.


D.

Request a change through the change control process to manage the new cybersecurityrequirements.


Expert Solution
Questions # 148:

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.

Evaluate demonstrated task accountability


B.

Determine the appropriate approach


C.

Analyze team member influence


D.

Identify levels of decision-making authority


Expert Solution
Questions # 149:

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.


B.

Review the process that resulted in this situation.


C.

Stop work until the design document is completed.


D.

Ask the team to document the design.


Expert Solution
Questions # 150:

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Options:

A.

Established ground rules before the discussion had started.


B.

Asked stakeholders not to voice their opinions during the meeting.


C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.


D.

Reinforced that higher-level management has the decision power.


Expert Solution
Viewing page 3 out of 13 pages
Viewing questions 101-150 out of questions