Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 3 out of 12 pages
Viewing questions 101-150 out of questions
Questions # 101:

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

Options:

A.

Perform a risk assessment and define a risk response action plan.


B.

Proceed with the project using management reserves to cover any delays or losses.


C.

Propose a pause in this phase to save labor costs and asset depreciation.


D.

Establish new partnerships with other suppliers in anticipation of any delays.


Expert Solution
Questions # 102:

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation


B.

Ask the stakeholders about the priority of this regulation


C.

Ask the product owner to include the requirements in the product backlog


D.

Ask the security department for details about regulations


E.

Ask the team members to include the requirements in the next iteration


Expert Solution
Questions # 103:

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

Options:

A.

Review the project scope and negotiate with the contractor


B.

Refuse the offer as it is included in the initial project scope


C.

Review the project costs and communicate this to the project sponsor


D.

Submit a change request to approve the offer


Expert Solution
Questions # 104:

Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished

What should the project manager have done differently?

Options:

A.

Formed a separate quality assurance team to test all items coming from each team at the end of each sprint


B.

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments


C.

Ensured frequent and continuous integration of work to obtain early feedback and continuous learning


D.

Arranged an online session on the integration concept and suggested tools to the teams


Expert Solution
Questions # 105:

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

Options:

A.

A directive style that makes decisions for the group to reach early outcomes


B.

A leadership style that coaches people who want help and fosters greater team collaboration


C.

A passive leadership style that allows the team to self-organize until the norming stage is reached


D.

A democratic style that uses techniques where majority opinion prevails


Expert Solution
Questions # 106:

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization

How should the project manager handle the different stakeholders?

Options:

A.

All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders


B.

Because there are different perspectives perform a stakeholder analysis and act based on the outcome.


C.

The project manager is working on the client's premises, so follow the directions of all the key stakeholders


D.

This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization


Expert Solution
Questions # 107:

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders


B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline


C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule


D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline


Expert Solution
Questions # 108:

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

Options:

A.

Networking


B.

Emotional intelligence


C.

Conflict management


D.

Influencing


Expert Solution
Questions # 109:

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

Options:

A.

Send this person to a meeting to negotiate the scope with the client


B.

Appreciate this team member’s performance throughout the project life cycle


C.

Promote this team member to a coaching role after this project is completed


D.

Document it in the team member’s end of year performance review


Expert Solution
Questions # 110:

A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

Question # 110


Expert Solution
Questions # 111:

A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again

What should the project lead do next?

Options:

A.

Notify senior management of the issues and have them review the importance of agreements with the team


B.

Challenge the team to determine if the issues surfaced again because agreements were not followed


C.

Post the agreements in a conspicuous place where all of the team members can see them.


D.

Let the team self-organize and determine the best means to prevent the issues from occurring again


Expert Solution
Questions # 112:

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.


B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain


C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.


D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue


Expert Solution
Questions # 113:

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

Options:

A.

Communicate directly with the director and inform them of the communications management plan


B.

Communicate directly with the client stating that any scope changes must go through the project manager


C.

Review the stakeholder engagement plan and put in place any existing actions

accordingly


D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes


Expert Solution
Questions # 114:

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?

Options:

A.

Develop a work plan for the project team member with the help of the resource manager


B.

Advise the functional manager and the project team member to review the resource management plan


C.

Tell the functional manager and the project team member to review the project

charter


D.

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member


Expert Solution
Questions # 115:

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

Options:

A.

Review lessons learned from previous projects that used the same team


B.

Review the organizational culture, structure, and governance


C.

Coordinate a meeting to understand the situation and resolve any conflicts.


D.

Coordinate a meeting with regional managers to ask for support


Expert Solution
Questions # 116:

A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline

What two actions should the project manager take'? (Choose two)

Options:

A.

Send letters to the neighbors and ask them kindly not to disturb the project.


B.

Set up a meeting with neighborhood representatives to win their cooperation


C.

Analyze the situation and find out what is causing the neighborhood's negative attitude.


D.

Ask the customer to extend the project deadline to allow time for conflict resolution


E.

Ask the mayor of the city to use their authority to stop neighborhood resistance


Expert Solution
Questions # 117:

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?

Options:

A.

Review the set of responsibilities with the team member


B.

Avoid the team member to prevent further conflicts


C.

Escalate the situation to the project sponsor


D.

Review the personnel skill documents


Expert Solution
Questions # 118:

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

Options:

A.

Introduce a recognition program to motivate and reward resource performance


B.

Enhance the competencies of the project team through training, mentoring and coaching.


C.

Increase the trained staff to create back-up for resources


D.

Meet with management to discuss dividing the project into smaller projects


E.

Convince senior management to hire third-party staff


Expert Solution
Questions # 119:

An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.

What should the project manager do to resolve this issue?

Options:

A.

Hire the resource in order to achieve the project objectives.


B.

Ask the client for a meeting and explain that the task will not be performed


C.

Evaluate the consequences and meet with the client to explain the possible scenarios.


D.

Try to accomplish the task internally by leveling resources from other projects


Expert Solution
Questions # 120:

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.

Increased bum rate


B.

Increased cost


C.

Increased technical debt


D.

Decreased efficiency


Expert Solution
Questions # 121:

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

Options:

A.

Update the communication styles for enrolled team members in the communications management plan.


B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)


C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.


D.

Update the resource calendar for enrolled team members in the resource management plan


Expert Solution
Questions # 122:

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.

What should the project manager do?

Options:

A.

Prepare and submit a status report to the steering committee to update performance monitoring


B.

Determine the data to be monitored during the project as well as the expected performance and targets.


C.

Update the communications management plan to consider performance review meetings with the project stakeholders


D.

Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project


Expert Solution
Questions # 123:

A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two)

Options:

A.

Revisit the team's discussion on team behaviors and norms


B.

Report to the project manager about the new team member’s behavior


C.

Coach the new team member to improve engagement with the team.


D.

Force the new team member to participate in activities that are considered easy


E.

Facilitate an open discussion on all ideas and perspectives


Expert Solution
Questions # 124:

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

Options:

A.

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend


B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them


C.

Continue emailing updated project status reports highlighting the key risks and

issues, and wait for the project sponsor to request a meeting


D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond


Expert Solution
Questions # 125:

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)

Options:

A.

Establish daily standups to review project progress and track the completion of deliverables


B.

Allow the team members to catch up at their own pace


C.

Alert the business stakeholders immediately of the schedule delay.


D.

Discuss the risk of project delay and work priorities with the respective functional managers


E.

Work with the team to identify options to accelerate project delivery.


Expert Solution
Questions # 126:

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.


B.

Provide a just-in-time training to the technician to improve their skill set.


C.

Use a direct, collaborative approach with the technician and supervisor.


D.

Replace the technician with a high performing resource as time is critical


Expert Solution
Questions # 127:

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

Options:

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting


B.

Reviewed all the approvals immediately after the kick-off meeting was over


C.

Ran separate kick-off meetings for each culture and time zone


D.

Validated each stakeholder's understanding during the kick-off meeting


Expert Solution
Questions # 128:

A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project

What should the project manager do first to determine a governance approach for the project?

Options:

A.

Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project


B.

Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines


C.

Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines


D.

Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project


Expert Solution
Questions # 129:

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

Options:

A.

Schedule a meeting for the project team to review the communications management plan.


B.

Tell the rest of the project team to continue discussions with the new team member


C.

Send an email to the project team outlining the communications strategy.


D.

Mentor the new team member on the methodology the project team is using


Expert Solution
Questions # 130:

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?

Options:

A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.


B.

Stop crashing the schedule


C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators


D.

Use a resource-levelling technique


Expert Solution
Questions # 131:

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

Options:

A.

Team A as they have calculated fewer story points than team B.


B.

Team B as they have calculated more story points than team A


C.

The team that completes the most stories selected from the sprint backlog


D.

The team with the least amount of defects in their deliverables


Expert Solution
Questions # 132:

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?

Options:

A.

Develop a business case with assumptions for the new model


B.

Develop a communications management plan to inform the employees about the new business model


C.

Adopt an iterative rollout approach that delivers the highest business value earlier


D.

Develop a detailed sprint plan with clear deliverables


Expert Solution
Questions # 133:

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?

Options:

A.

Update the issue log and act to minimize the impact


B.

Update the schedule to include the delay


C.

Add the risk and the delay to the risk register


D.

Escalate to the management team for delay approval


Expert Solution
Questions # 134:

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

Options:

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them


B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.


C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report


D.

Research which templates of reports were used the most for this framework and incorporate them into the project


Expert Solution
Questions # 135:

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables


B.

Request more funding from the project sponsor to hire additional skilled resources

and to incorporate additional quality in the project delivery approach and outcome


C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions


D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives


Expert Solution
Questions # 136:

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

Options:

A.

Hold a stakeholder meeting to align timelines and scope expectations.


B.

Crash the schedule to shorten the timeline while keeping the scope unchanged


C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.


D.

Reduce the scope of the project by removing activities and shortening the timeline


Expert Solution
Questions # 137:

A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client’s decision to keep the project active? (Choose two)

Options:

A.

Alternatives analysis


B.

Voting


C.

Cost-benefit analysis


D.

Multi-criteria decision making


E.

Autocratic decision making


Expert Solution
Questions # 138:

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?

Options:

A.

Involved the key stakeholders in the decision-making process


B.

Customized stakeholder communications based on the stakeholders’ needs


C.

Analyzed the changes in stakeholder attributes


D.

Documented the project vision and objectives


Expert Solution
Questions # 139:

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

Options:

A.

Retrospect frequently and suggest improvements.


B.

Incorporate a predictive approach for this element.


C.

Implement mitigation strategies for this element


D.

Request additional team members to help with improvements


Expert Solution
Questions # 140:

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.


B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly


C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties


D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer


Expert Solution
Questions # 141:

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.


B.

Encourage and assign the team to perform demos of their products or software with the customers


C.

Give the team autonomy to make their own decisions on how to perform the tasks.


D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task


Expert Solution
Questions # 142:

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Options:

A.

Check the approved list of requirements to see if there are any missing items.


B.

Work with the stakeholder to improve the requirements' acceptance criteria


C.

Review the requirements traceability matrix with the concerned stakeholder


D.

Discuss with the stakeholder which additional requirements should be added


Expert Solution
Questions # 143:

Drag the to the correct scenario on the right

Question # 143


Expert Solution
Questions # 144:

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)

Options:

A.

Independent personal testing


B.

Security and performance testing


C.

An experimental approach to cover all possible choices


D.

Story testing


E.

Tests based on behavior and test-driven development


Expert Solution
Questions # 145:

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.

Add the competitor's functionalities to the product backlog to improve the product


B.

Ask the sponsor to add more people to the team


C.

Help the team to find a new approach to launch the product as soon as possible


D.

Ask the team to increase the velocity to launch the product as soon as possible


Expert Solution
Questions # 146:

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.

Reduce the priority of project risks as all remaining risks are low-level


B.

Notify stakeholders that all high-level risks have been resolved


C.

Reevaluate identified risks and update the risk register


D.

Reclassify low-level risks as high-level risks


Expert Solution
Questions # 147:

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

Options:

A.

Consult the project scope document to make sure the addition is in scope.


B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list


C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.


D.

Engage the stakeholder to solicit more information before responding to the request


Expert Solution
Questions # 148:

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

Options:

A.

Determine which agile software tools will be required to support agile delivery within the organization


B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project


C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted


D.

Determine how to transform the organization using agile techniques, including organizational training and communications


Expert Solution
Questions # 149:

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Question # 149


Expert Solution
Questions # 150:

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Question # 150


Expert Solution
Viewing page 3 out of 12 pages
Viewing questions 101-150 out of questions