Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 3 out of 13 pages
Viewing questions 101-150 out of questions
Questions # 101:

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?

Options:

A.

Register the issue as a risk with the project team members.


B.

Review the project schedule with project team members and the suppliers.


C.

Advise the procurement department to develop a new supplier strategy.


D.

Use the procurement and risk management plans to manage this issue.


Expert Solution
Questions # 102:

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?

Options:

A.

Engage with each project team member to explain the individual consequences of late delivery.


B.

Establish a daily standup meeting where each project team member reports their progress.


C.

Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.


D.

Empower each project team member with ownership of a particular aspect of the project.


Expert Solution
Questions # 103:

A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with

another team to ensure the continuity of deliverables.

What should the project manager do?

Options:

A.

Merge both teams into one team so the knowledge is commonly available.


B.

Remove the dependency to eliminate the need for knowledge sharing.


C.

Redistribute the team members so knowledge is available in both teams.


D.

Request the respective teams to plan for knowledge-sharing sessions.


Expert Solution
Questions # 104:

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Register an issue and escalate it to the project sponsor.


B.

Invite the stakeholders to discuss a new prioritization.


C.

Estimate the management to replace the customer service manager.


D.

Increase the team capacity to finish the project on time.


Expert Solution
Questions # 105:

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.

Ask the team to raise blockers or impediments in daily meetings.


B.

Prioritize deliverables based on business value and define frequent releases.


C.

Ask the team to challenge the project estimations for a faster delivery.


D.

Prioritize the tasks with high risks to reduce the number of iterations required.


Expert Solution
Questions # 106:

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not

available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

Options:

A.

Ask the customer to review the deliverables in each iteration based on their availability.


B.

Request the customer to clarify all requirements at the start of each iteration.


C.

Plan ahead and define the best way to review the deliverables with the customer.


D.

Include the customer in daily project activities to gain the required guidance.


Expert Solution
Questions # 107:

A project manager is leading a project team composed of members with varying levels of knowledge and

experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.

What should the project manager do?

Options:

A.

Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.


B.

Ask each experienced member to be the mentor to one of the less-experienced members.


C.

Ask the more experienced members to review all of the tasks performed by the less-experienced members.


D.

Ask the resource manager to replace the less-experienced members with more experienced team members.


Expert Solution
Questions # 108:

During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.

What should the project manager do?

Options:

A.

Ensure team B prioritizes the dependent activity in iteration three.


B.

Include the dependent activity in the current iteration for team B.


C.

Assign the two critical activities to team B in iteration two.


D.

Cancel the current iteration and reschedule it with the dependent activity.


Expert Solution
Questions # 109:

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.

Assign the task to someone else on the team.


B.

Discuss it with the team member in confidence.


C.

Discuss this matter during the project meeting.


D.

Include this item in the risk register.


Expert Solution
Questions # 110:

A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.

What should the project manager do first?

Options:

A.

Relax the OHS requirements as the client is not concerned.


B.

Discuss the OHS requirements with the client.


C.

Apply the same OHS requirements as the previous project.


D.

Discuss the OHS requirements with the regulatory organization.


Expert Solution
Questions # 111:

Drag the items on left side to the matching term within the correct project approach on the right side.

Question # 111


Expert Solution
Questions # 112:

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

Options:

A.

Request a budget extension to get local resources experienced in agile.


B.

Plan to have the agile resources temporarily relocate to the project manager's location.


C.

Engage the agile resources through video conferencing on a daily basis.


D.

Advise the sponsor that the project will be delayed as agile training will be required.


Expert Solution
Questions # 113:

A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.

What should the project manager have done to prevent this?

Options:

A.

Incorporated sufficient schedule reserves based on similar delays in past projects.


B.

Appointed a senior environmental compliance officer to report directly to the project manager.


C.

Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.


D.

Approached the regulator for a partial waiver in light of the environmental importance of the project.


Expert Solution
Questions # 114:

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

Options:

A.

Social media


B.

Email


C.

Meetings


D.

Newspapers


Expert Solution
Questions # 115:

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?

Options:

A.

Follow the Perform integrated Change Control process and submit a change request


B.

Ask the team members to draft a justification before processing the reimbursements


C.

Update the project management plan with the incurred costs


D.

Review the budget and allocate funds for the reimbursements


Expert Solution
Questions # 116:

A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within

the organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the

projects to use more agile methodologies.

Before mandating any agile methods to be used in a project, what should the project manager do first?

Options:

A.

Provide agile training to those who will be part of the project team.


B.

Shift all existing projects to agile methodologies with a strict timeline.


C.

Pause the current projects to align them to the new agile cadence.


D.

Assess the organizational culture and readiness for the transformation.


Expert Solution
Questions # 117:

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

Options:

A.

Invite the director to attend the daily standup meetings.


B.

Share this with the team and ask them to develop reports for the director.


C.

Introduce the agile aspect to the director and agree on a solution.


D.

Explain to the director that agile projects have live reports.


Expert Solution
Questions # 118:

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Options:

A.

Functional managers, team members, and external consultants with experience in the field


B.

Team members, engineers, and weather experts


C.

Team members, consultants from outside the project with experience in the field, and the customer


D.

Weather experts, functional managers, and team members


Expert Solution
Questions # 119:

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.

What should the project manager establish first in the project governance structure?

Options:

A.

Clear responsible, accountable, consult, and inform (RACI) matrix


B.

Risk management and issues resolution plan


C.

Resource management and conflict resolution plan


D.

Clear project work breakdown structure (WBS) and timeline


Expert Solution
Questions # 120:

A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution

team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.

What should the project manager do next to deliver a reliable solution?

Options:

A.

Meet with the resources and agree that the more experienced resource's approach has proven to be effective in the past.


B.

Meet with each resource's functional manager and arrive at a common approach that is appropriate for the project's constraints.


C.

Meet with the entire project team and decide on a further course of action based on team consensus.


D.

Meet with the resources together and find common ground on viewpoints to compromise on an approach.


Expert Solution
Questions # 121:

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Defined the skill requirements more clearly in the scope statement.


B.

Asked the manager to follow the agreed-upon resource management plan.


C.

Conducted periodic reviews with the manager on resource availability.


D.

Consulted with the installation team on a regular basis to check for conflicts.


Expert Solution
Questions # 122:

During project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?

Options:

A.

Escalate the issue to the project sponsor for resolution.


B.

Meet with the team to discuss alternatives.


C.

Hold the team accountable and ask for an immediate solution.


D.

Remove the deliverable from the project scope.


Expert Solution
Questions # 123:

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

Options:

A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.


B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.


C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.


D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.


Expert Solution
Questions # 124:

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

Options:

A.

Prioritize the projects, giving higher priority to projects that will increase profit.


B.

Make sure the project is fast tracked so that slipped time lines are recovered.


C.

Request that upper management hire additional staff to support the projects.


D.

Ensure that all of the projects are of high quality and are delivered on time.


Expert Solution
Questions # 125:

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

Options:

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.


B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.


C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.


D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.


Expert Solution
Questions # 126:

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.

What should the project manager do to keep the stakeholders engaged?

Options:

A.

Use email as a communication channel.


B.

Use feedback and decision-making tools.


C.

Use meetings as a communication channel.


D.

Use a shared collaboration platform.


Expert Solution
Questions # 127:

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins

to identify, evaluate, and categorize the stakeholder relationships to the program.

What is the purpose of this process?

Options:

A.

Identify all stakeholders who can negatively affect the project.


B.

Incorporate the needs of all stakeholders into the communications management plan.


C.

Incorporate only primary stakeholders into the communications management plan.


D.

Identify all stakeholders who can positively affect the project.


Expert Solution
Questions # 128:

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

What should the project manager do to obtain agreement from both companies and acceptance from marketing?

Options:

A.

Create a special release 4 weeks after the current release to deliver the new feature in its entirety.


B.

Stop the current release work for 4 weeks in order to work and deliver the new feature completely.


C.

Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.


D.

Add the new feature to the list for the next release and continue working on the current release.


Expert Solution
Questions # 129:

An agile project is in its ninth of 10 iterations. The team is delivering the work as expected. In the planning session, the team identifies a dependency with another project in the organization.

What should the scrum master do in order to accomplish the iteration goal?

Options:

A.

Ask the product owner to collaborate with the other team about the dependency.


B.

Recommend that the product owner change the priority of the dependency.


C.

Initiate collaboration with the other project team working on the dependency.


D.

Ask a team member to interact with the other team to complete the dependency.


Expert Solution
Questions # 130:

An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.

How should the facilitator proceed?

Options:

A.

Schedule a release planning session.


B.

Set up a lessons learned session from a similar project.


C.

Conduct a product roadmap session with the team.


D.

Hold a team charter discussion.


Expert Solution
Questions # 131:

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

Options:

A.

Reject the changes and stay the original course as initially agreed with the client.


B.

Review the changes and make the decision based on the project team's recommendations.


C.

Discuss the changes with the client and jointly make the decision on how to proceed.


D.

Review the risk register to see if mitigations have already been outlined for this scenario.


Expert Solution
Questions # 132:

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?

Options:

A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.


B.

Establish a pull communications method to access knowledge repositories and lessons learned.


C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.


D.

Establish a push communications method for the team to share knowledge and lessons learned.


Expert Solution
Questions # 133:

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not

shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?

Options:

A.

Lack of team member training on documentation planning


B.

Improper assignment of tasks to team member pairings


C.

Incorrect communication techniques applied during implementation


D.

Team cohesiveness was lost because team members worked in pairs


Expert Solution
Questions # 134:

A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the

importance of the project meeting the company's strategy, investment, and compliance requirements.

What should the project manager do?

Options:

A.

Replicate the organizational governance to the project governance.


B.

Put into place a project governance model in line with the requirements.


C.

Create an organizational project management governance.


D.

Ask the organization to create a project portfolio governance.


Expert Solution
Questions # 135:

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

Options:

A.

Ensure that the schedule is aligned with the vision and objectives.


B.

Escalate the compliance issue to the project management office (PMO).


C.

Congratulate the team and move on to the execution phase.


D.

Develop a new detailed schedule with the team and project sponsor.


Expert Solution
Questions # 136:

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.


B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.


C.

Document the kick-off meeting and close out the planning phase after the meeting is held.


D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.


Expert Solution
Questions # 137:

A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,

the budget becomes the primary concern due to currency instability in the country.

What should the project manager do next?

Options:

A.

Evaluate the situation with the team


B.

Escalate the risk to the project sponsor


C.

Use the project's contingency reserve


D.

Ask for additional budget from the client


Expert Solution
Questions # 138:

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

Options:

A.

Travel to the development team's office to push the schedule.


B.

Set up a meeting with key stakeholders to clarify requirements.


C.

Escalate to the project steering committee and request additional time.


D.

Create prototypes with the development team to confirm requirements.


Expert Solution
Questions # 139:

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Options:

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.


B.

Revise the project management plan and move the task to a time when the technical resource will be available.


C.

Consult the risk register for an appropriate planned risk response and implement.


D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.


Expert Solution
Questions # 140:

A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.

Which scheduling method should the project manager use to develop the schedule?

Options:

A.

Iterative scheduling


B.

Three-point scheduling


C.

Parametric scheduling


D.

Analogous scheduling


Expert Solution
Questions # 141:

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project

manager do to avoid this in the future?

Options:

A.

Schedule weekly project status meetings with all stakeholders including the customer and internal resources.


B.

Include the project stakeholders’ needs while planning the project communications strategy.


C.

Designate a team member to respond to the emails from these stakeholders.


D.

Include the stakeholders’ emails in all of the project status communications.


Expert Solution
Questions # 142:

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.

How should the project lead respond?

Options:

A.

The cost performance index (CPI) is below average with a 25% reduction.


B.

The schedule performance index (SPI) is 25% less than expected.


C.

The team's performance indicator is higher than expected.


D.

The cost and schedule performance indicators are equivalent.


Expert Solution
Questions # 143:

While monitoring a project at a work site, the project manager notices that the site team’s work breaks have increased by a few minutes every week. How should the project

manager approach this?

Options:

A.

Reduce payment to the workers due to their extended breaks.


B.

Issue a formal written warning to all hourly workers for their break tardiness.


C.

Have a meeting with the team to discuss the issue and propose solutions.


D.

Dismiss some of the workers for failing to adhere to the break policy.


Expert Solution
Questions # 144:

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

Options:

A.

By scheduling iterative meetings with the product owner to improve project tracking


B.

By focusing on the delivery of incremental working products lo the customer


C.

By reviewing burnup charts to determine the effort required against estimated earned value


D.

By conducting daily standups to more accurately track project deliverables


Expert Solution
Questions # 145:

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

Options:

A.

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.


B.

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.


C.

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.


D.

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.


Expert Solution
Questions # 146:

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause

analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.

What should the project manager do next?

Options:

A.

Review the change control process to ensure quality management artifacts are updated as part of the change.


B.

Review the quality management process and perform a process audit as part of ongoing quality assurance.


C.

Review the communications management plan to ensure change requests are communicated to the affected team members.


D.

Review the quality management process with the project management office (PMO) to ensure compliance with best practices.


Expert Solution
Questions # 147:

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?

Options:

A.

Assess and prioritize the impact of the new law on the project plan.


B.

Update the project plan because the law is an obligation for the project.


C.

Minimize the scope to catch the cost and schedule baseline.


D.

Meet the sponsor to ask for additional time and budget increase.


Expert Solution
Questions # 148:

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government

official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include

aspects that the previous project sponsor did not support.

What should the project manager do next?

Options:

A.

Meet with the new project sponsor to review the current project scope and the requested changes.


B.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.


C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.


D.

Inform the new project sponsor that the new aspects will not be included in this project.


Expert Solution
Questions # 149:

A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.

How should the project manager resolve this conflict and reach a consensus?

Options:

A.

Escalate this to senior management and ensure that the team's acceptance is achieved.


B.

Communicate to the two teams that the tool has won per the selection process and they need to accept the outcome.


C.

Ignore the conflict as the tool is selected per the proposal guidelines and the project is complete.


D.

Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.


Expert Solution
Questions # 150:

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

Options:

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.


B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.


C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.


D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.


Expert Solution
Viewing page 3 out of 13 pages
Viewing questions 101-150 out of questions