PMI Project Management Professional (2025 Version) PMP Question # 138 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 138 Topic 14 Discussion

PMP Exam Topic 14 Question 138 Discussion:
Question #: 138
Topic #: 14

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?


A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future


B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing


C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch


D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.