New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 138 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 138 Topic 14 Discussion

PMP Exam Topic 14 Question 138 Discussion:
Question #: 138
Topic #: 14

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?


A.

Travel to the development team's office to push the schedule.


B.

Set up a meeting with key stakeholders to clarify requirements.


C.

Escalate to the project steering committee and request additional time.


D.

Create prototypes with the development team to confirm requirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.