Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 138 Topic 14 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 138 Topic 14 Discussion

PMP Exam Topic 14 Question 138 Discussion:
Question #: 138
Topic #: 14

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?


A.

Explore the minimum requirements of the product and their feasibility.


B.

Explain the resource constraints of the project to management.


C.

Outsource the management of the product to an external team.


D.

Conduct a detailed risk analysis to highlight the risks in the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.