PMI Project Management Professional (2025 Version) PMP Question # 138 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 138 Topic 14 Discussion

PMP Exam Topic 14 Question 138 Discussion:
Question #: 138
Topic #: 14

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?


A.

Escalate the issue to the change control board (CCB).


B.

Ask the project team to analyze the impact.


C.

Register the risk and document the contingency plan.


D.

Have the project team brainstorm alternatives.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.