PMI Project Management Professional (2025 Version) PMP Question # 143 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 143 Topic 15 Discussion

PMP Exam Topic 15 Question 143 Discussion:
Question #: 143
Topic #: 15

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?


A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.


B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea


C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.


D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.