Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 143 Topic 15 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 143 Topic 15 Discussion

PMP Exam Topic 15 Question 143 Discussion:
Question #: 143
Topic #: 15

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?


A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.


B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.


C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.


D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.