PMI Project Management Professional (2025 Version) PMP Question # 143 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 143 Topic 15 Discussion

PMP Exam Topic 15 Question 143 Discussion:
Question #: 143
Topic #: 15

A new project manager has been assigned to an ongoing project because of the promotion of their predecessor. The new project manager needs to understand the levels of decision-making authority on the team.

Which document should the incoming project manager review?


A.

Resource management plan


B.

Communications management plan


C.

Information management plan


D.

Stakeholder engagement plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.