Question #: 140
Topic #: 15

A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with their project tasks.

What should the project manager do first?


A.

Issue a formal complaint to the project sponsor claiming a lack of proper tools.


B.

Meet with the IT team to evaluate how fast the software license can be renewed.


C.

Ask the team to fast-track the project and perform tasks that do not require calculations.


D.

Ask the team members to find an alternative way to perform calculations.