Question #: 145
Topic #: 15

A project manager is leading a long-term project, executed in stages, to set up a complex communications network in many rural areas. The project is being executed in stages.

What should the project manager do to ensure that monetized business value is generated as planned?


A.

Compare the estimate to complete (ETC) benefits against the project business plan


B.

Compare the benefits of the throughput analysis against the project business plan


C.

Evaluate the net promoter score (NPS) benefits against the project business plan


D.

Evaluate the generated benefits at project milestones against the project business plan