PMP Exam Topic 15 Question 145 Discussion:
Question #: 145
Topic #: 15

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?


A.

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.


B.

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.


C.

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.


D.

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer: