Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 124 Topic 13 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 124 Topic 13 Discussion

PMP Exam Topic 13 Question 124 Discussion:
Question #: 124
Topic #: 13

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?


A.

Shared


B.

Accepted


C.

Enhanced


D.

Exploited


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.