Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 124 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 124 Topic 13 Discussion

PMP Exam Topic 13 Question 124 Discussion:
Question #: 124
Topic #: 13

A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed.

What should the project manager do next?


A.

Accept the demands and remove the junior team member.


B.

Encourage further and deeper discussions among team members.


C.

Group the new team members together for training purposes.


D.

Remove possible conflicts from future project assignments.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.