PMI Project Management Professional (2025 Version) PMP Question # 124 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 124 Topic 13 Discussion

PMP Exam Topic 13 Question 124 Discussion:
Question #: 124
Topic #: 13

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features

What should the project manager do to avoid this in the future?


A.

Set up requirements-gathering sessions with all key stakeholders to evaluate the scope once again and reprioritize the backlog based on the sessions.


B.

Schedule adequate sprint demos to gather early feedback from the stakeholders and adapt the plan accordingly


C.

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.


D.

Evaluate the team's skills to look for someone with experience in product design and assign that person the task of rebuilding the product interface


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.