PMI Project Management Professional (2025 Version) PMP Question # 125 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 125 Topic 13 Discussion

PMP Exam Topic 13 Question 125 Discussion:
Question #: 125
Topic #: 13

A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint.

How should the project manager help the team resolve the issue?


A.

Direct the senior-most member to determine the scope on behalf of the team.


B.

Discuss this with the team and decide what the scope of the feature should be.


C.

Ask the team to log the story in the product backlog and move on to the next feature.


D.

Encourage the team to collaborate to resolve their understanding of the feature.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.