Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 229 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 229 Topic 23 Discussion

PMP Exam Topic 23 Question 229 Discussion:
Question #: 229
Topic #: 23

A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?


A.

Assign the challenging tasks to the team member.


B.

Ask the product owner to assign the challenging tasks.


C.

Reprioritize the challenging tasks to future sprints.


D.

Coach the team member to pick up the challenging tasks.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.