PMI Project Management Professional (2025 Version) PMP Question # 119 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 119 Topic 12 Discussion

PMP Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?


A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports


B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members


C.

Reinforce with the key stakeholder that the project is performing on schedule\


D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.