PMP Exam Topic 13 Question 121 Discussion:
Question #: 121
Topic #: 13

The project manager of a globally dispersed team evaluates the organization's current virtual engagement tools and strategies. A couple of the remote team members are not participating effectively in virtual meetings.

Which action should the project manager take to improve remote engagement?


A.

Implement a new suite of collaboration tools to provide various communication options for the team.


B.

Organize an in-person, team-building event to improve team engagement and communication.


C.

Schedule one-on-one meetings with the team members to understand their specific needs and challenges.


D.

Survey all team members to identify common issues with virtual engagement and address them systematically.