New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 94 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 94 Topic 10 Discussion

PMP Exam Topic 10 Question 94 Discussion:
Question #: 94
Topic #: 10

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?


A.

Support the team in identifying the area of development and address the gap.


B.

Dissolve the team and include the team members in other existing teams.


C.

Identify the struggling team members and move them out of the team.


D.

Set up a clear expectation that the team is to deliver as in their previous projects.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.