PMI Project Management Professional (2025 Version) PMP Question # 94 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 94 Topic 10 Discussion

PMP Exam Topic 10 Question 94 Discussion:
Question #: 94
Topic #: 10

An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?


A.

Reschedule the project until the local travel restrictions are lifted.


B.

Schedule virtual sessions with the specialist to guide the team in completing the activity.


C.

Seek additional budget to train the project team on the required skill set.


D.

Refer to the organization's lessons learned repository and find an alternative solution.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.