New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 123 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 123 Topic 13 Discussion

PMP Exam Topic 13 Question 123 Discussion:
Question #: 123
Topic #: 13

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?


A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.


B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.


C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.


D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.