PMI Project Management Professional (2025 Version) PMP Question # 123 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 123 Topic 13 Discussion

PMP Exam Topic 13 Question 123 Discussion:
Question #: 123
Topic #: 13

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?


A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session


B.

Contact the project sponsor and request new team members who are familiar with adaptive projects


C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project


D.

Freeze the design stage and look for an external resource to run iterative design at extra cost


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.