A company faces challenges and decides to cut a few product features from the main project due to market conditions. During a status meeting, a new stakeholder expresses concern about the discrepancies between the current deliverables and the deliverables agreed upon in the project charter.

What should the project manager do first?


A.

Ask the project team to increase the number of updates provided to the stakeholder.


B.

Determine the root cause of the discrepancy with the project team and agree on the project scope.


C.

Ask the new stakeholder to submit a change request to the change control board (CCB).


D.

Review the project objectives for alignment with the intended corresponding business value.