PMI Project Management Professional (2025 Version) PMP Question # 137 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 137 Topic 14 Discussion

PMP Exam Topic 14 Question 137 Discussion:
Question #: 137
Topic #: 14

A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,

the budget becomes the primary concern due to currency instability in the country.

What should the project manager do next?


A.

Evaluate the situation with the team


B.

Escalate the risk to the project sponsor


C.

Use the project's contingency reserve


D.

Ask for additional budget from the client