New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 120 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 120 Topic 13 Discussion

PMP Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution

team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.

What should the project manager do next to deliver a reliable solution?


A.

Meet with the resources and agree that the more experienced resource's approach has proven to be effective in the past.


B.

Meet with each resource's functional manager and arrive at a common approach that is appropriate for the project's constraints.


C.

Meet with the entire project team and decide on a further course of action based on team consensus.


D.

Meet with the resources together and find common ground on viewpoints to compromise on an approach.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.