Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 120 Topic 13 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 120 Topic 13 Discussion

PMP Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?


A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.


B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.


C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,


D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.