PMI Project Management Professional (PMBOK 7th Version) PMP Question # 114 Topic 12 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 114 Topic 12 Discussion

PMP Exam Topic 12 Question 114 Discussion:
Question #: 114
Topic #: 12

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?


A.

Maintain a central repository of artifacts with a version control system.


B.

Maintain separate document control via regions to avoid discrepancies.


C.

Develop a document management software for version control.


D.

Facilitate training on version control and project artifacts,