PMI Project Management Professional (2025 Version) PMP Question # 114 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 114 Topic 12 Discussion

PMP Exam Topic 12 Question 114 Discussion:
Question #: 114
Topic #: 12

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?


A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.


B.

Stop crashing the schedule


C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators


D.

Use a resource-levelling technique


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.