A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?


A.

Brainstorming


B.

Meetings


C.

Regression analysis


D.

Expert judgment