New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 101 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 101 Topic 11 Discussion

PMP Exam Topic 11 Question 101 Discussion:
Question #: 101
Topic #: 11

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?


A.

Register the issue as a risk with the project team members.


B.

Review the project schedule with project team members and the suppliers.


C.

Advise the procurement department to develop a new supplier strategy.


D.

Use the procurement and risk management plans to manage this issue.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.