New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 142 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 142 Topic 15 Discussion

PMP Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.

How should the project lead respond?


A.

The cost performance index (CPI) is below average with a 25% reduction.


B.

The schedule performance index (SPI) is 25% less than expected.


C.

The team's performance indicator is higher than expected.


D.

The cost and schedule performance indicators are equivalent.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.