PMI Project Management Professional (2025 Version) PMP Question # 142 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 142 Topic 15 Discussion

PMP Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

PMP Question 142


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.