Question #: 115
Topic #: 12

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?


A.

Follow the Perform integrated Change Control process and submit a change request


B.

Ask the team members to draft a justification before processing the reimbursements


C.

Update the project management plan with the incurred costs


D.

Review the budget and allocate funds for the reimbursements